The hydraulic system at Casa del Forno centres on a heat pump located in the boiler room, providing hot water to all bathrooms and radiators with minimal thermal dispersion due to strategic pipe routing.

Hydraulic System

Overview

The hydraulic system at Casa del Forno is designed for efficiency and minimal heat loss. All water heating and distribution originates from the Boiler Room, where a heat pump provides hot water for the entire property.

Heat Pump System

Location: Boiler Room

The heat pump is installed in the Boiler Room (locale caldaia), which is strategically positioned in the basement of Casa del Forno. This location was chosen because:

  • Central position beneath the main apartments
  • Direct vertical access to Sub 5 bathroom above
  • Immediate horizontal access to Sub 7 bathroom adjacent
  • Minimal pipe runs = minimal thermal dispersion

Hot Water Distribution

From the Boiler Room, hot water pipes are distributed to:

DestinationConnection TypeDistanceNotes
Sub 5 BathroomVertical (straight up)MinimalDirectly above boiler room
Sub 7 BathroomHorizontal (adjacent)MinimalImmediately next to boiler room
Outdoor BathroomDedicated runShortHot and cold water supply

TIP

Thermal Efficiency: By positioning all bathrooms close to the boiler room, we achieve minimal thermal dispersion in the hot water system. This means faster hot water delivery and reduced energy waste.

Radiator Heating System

The boiler room also houses the connection point for the radiator heating system. From this central location:

  • Pipes distribute heated water to radiators throughout the apartments
  • The heat pump provides consistent heating during colder months
  • Integration with woodstove heating in individual rooms provides backup

Outdoor Bathroom Connection

The Outdoor Bathroom receives its water supply directly from the boiler room:

ServiceDescription
Hot WaterSupplied via dedicated pipes from heat pump
Cold WaterStandard cold water supply line
DrainageConnected to main waste system

This ensures the outdoor bathtub, shower, and WCs have full hot and cold water availability year-round.

Drainage and Waste System

CAUTION

Critical Issue: Septic Tank Must Be Replaced

The current drainage system uses a septic tank (fossa biologica), which is not acceptable for our requirements. This must be modified to connect to the main sewer system.

Current Problem

  • Current drainage flows to a septic tank
  • This is inadequate for our usage requirements
  • Does not meet modern standards

Required Modification

The main sewer connection is located only 3 metres from the current pipe routing. The modification requires:

  1. Redirect existing pipes from the septic tank route
  2. Connect to the main sewer (fognatura) located 3m away
  3. Ensure all drainage from bathrooms and kitchens flows to the sewer
Current StateRequired State
Septic tank (fossa biologica)Main sewer connection (fognatura)
Limited capacityUnlimited municipal drainage
Maintenance requiredLow maintenance

IMPORTANT

This sewer connection is a priority modification that must be completed before full occupancy of the property.

System Diagram

                    ┌─────────────────────┐
                    │    BOILER ROOM      │
                    │   (Locale Caldaia)  │
                    │                     │
                    │    [HEAT PUMP]      │
                    │         │           │
                    └─────────┼───────────┘
                              │
          ┌───────────────────┼───────────────────┐
          │                   │                   │
          ▼                   ▼                   ▼
    ┌──────────┐       ┌──────────┐       ┌──────────────┐
    │  SUB 5   │       │  SUB 7   │       │   OUTDOOR    │
    │ BATHROOM │       │ BATHROOM │       │   BATHROOM   │
    │ (above)  │       │(adjacent)│       │              │
    └──────────┘       └──────────┘       └──────────────┘
          │                   │                   │
          └───────────────────┴───────────────────┘
                              │
                              ▼
                    ┌─────────────────────┐
                    │   MAIN SEWER        │
                    │   (3m away)         │
                    │   NOT septic tank   │
                    └─────────────────────┘

Apartments

  • Sub 5 - Bathroom directly above boiler room
  • Sub 7 - Bathroom adjacent to boiler room
  • Sub 6 - Kitchen facilities